eleQtra 20 MW Solar Project Development
Solution
Lima Partners provided consultancy services for eleQtra's La Honda 20 MW Solar Project in Tamale. The project deliverables included:
- Liaising with Electricity Company of Ghana for the signing of the Power Purchase Agreements
- Coordinating the attempt to finalise a Government Consent & Support Agreement (GCSA)
- Involvement with planned Fuel Supply Agreement negotiation
- Involvement in the short listing and selection of an Engineering, Procurement and Construction (EPC) contractor
- Advising the sponsors / shareholders on project structuring and tax maximisation approach
- Coordinating Environmental Impact Assessment (EIA) process with the environmental advisor and EPA
- Coordinating site investigations, Geotechnical and other studies
- Assistance with tax exemption application process, including the preparation of the exemption application pack for cabinet
- Assistance with ongoing discussion with potential lenders